25/09/09
The Luggage end bodywork was moved along the frames today to expose the other end. Pictures below show that the framework uncovered is in fairly good condition and should only need a small amount of work to complete. This work may be completed following return to West Somerset unless time permits.
Luggage end Framework exposed for the first time
Work has continued on the Driving end including Brake Gear and Vacuum pipework, buffers are now refitted.
More pictures of work up to 01/10/2009 are shown below. Supplied by Ian Grady
L: Work underway on Luggage end R Vacuum and steam heat pipework refitted
Frames returned to WSR 05/11/2009